In so far as the Ministry of the Solicitor General of Canada is concerned, the answer is as follows:
(a) In the case of Amos detachment, the projected construction cost was $924,000. In the case of Rouyn-Noranda, the projected construction cost was $1.1 million.
(b) The construction costs for a new detachment in Amos were included in the 1995/96 capital construction program budget as well as the main estimates, at a total cost of $924,000 with $374,000 to be spent in 1995/96.