I wanted to mention this, and then I am going to turn it over to Mr. Howden for the specifics of the start-up. When we look at the issues of the act, the commission was not consulted on the act. We received copies just very recently and we did not have legal counsel because justice took it away. It thought there was going to be dispute over this bill. Therefore, we do not have legal counsel to review this matter.
When the commission looks at this, we absolutely agree with AECL, that it is responsible for the safety of the establishments. We absolutely concur with that. We require it to be that way. Because this reactor would not, under the present licence, be licensable with one pump, it is of very great interest that it will not be within the licensing basis. This licence is not going to be applicable for this area, so what exactly does the commission do? That is exactly what we will look at.
Mr. Howden will speak to the issue of the start-up.