Mr. Speaker, in response to (a)(i), a total of 85 projects were approved during fiscal year 2010-11, and a total of 23 projects approved for fiscal year 2011-12.
In response to (a)(ii), the budget for fiscal year 2010-11 was $107,256,520 and for fiscal year 2011-12 is $91,396,000.
In response to (a)(iii), the budget for fiscal year 2012-13 is $92,696,000.
In response to (b)(i), a total of 11 projects were approved during fiscal year 2010-11, and a total of 4 projects approved for fiscal year 2011-12.
In response to (b)(ii), the budget for fiscal year 2010-11 was $13,700,000 and for fiscal year 2011-12 is $13,700,000.
In response to (b)(iii), the budget for fiscal year 2012-13 is $8,000,000.
In response to (c) (i),a total of 29 projects were approved during fiscal year 2010-11, and a total of 5 projects approved for fiscal year 2011-12.
In response to (c)(ii), the budget for fiscal year 2010-11 was $5,000,000 and for fiscal year 2011-12 is $5,000,000.
In response to (c)(iii), the budget for fiscal year 2012-13 is $5,000,000.
A project is considered 'approved' if it has gone through all of the required levels of approvals and is either initiated, ongoing, or closed within a given fiscal year.
Fiscal year 2011-12 is not yet complete therefore data provided is a partial response.
For specific information on the projects approved by START with a value of more than$ 25,000, please refer to the proactive disclosure section of the Department of Foreign Affairs and International Trade Canada website: http://w03.international.gc.ca/dg-do/index_fa-ae.aspx?lang=eng&p=3&r=r.