Mr. Speaker, with regard to part (a), on November 13, 2017, the CCGS Hudson arrived at its home base of Dartmouth, Nova Scotia. Further work, which has been planned for many months, will be undertaken on the Hudson in preparation for its 2018 programming which is projected to commence on April 4, 2018.
With regard to part (b), the refit of the vessel did not meet its original completion date, as the refit work being carried out by a contractor was not completed on time.
With regard to part (c), the contract for the refit has not been amended to increase the budget. A determination of the final budget cannot be made at this time, as Public Services and Procurement Canada is reviewing the terms of the contract with the original shipyard.
With regard to part (d), a total of seven science missions were impacted due to the unavailability of the CCGS Hudson for the 2017 field season. Of those, one mission was conducted on another Coast Guard vessel, four requests for proposals were issued to carry out other missions on charter vessels, one mission was cancelled outright, and another mission was substantially reduced.
With regard to part (e), the two missions involving cancellations are as follows. The majority of the Atlantic zone off-shelf monitoring program, AZOMP, mission scheduled for May 2017 was cancelled as the initial attempt to charter a vessel was unsuccessful. Some of the high-priority activities, namely the recovery of a subsurface oceanographic mooring and the deployment of Argo floats in the Labrador Sea, have been rescheduled on other Coast Guard vessels. The Natural Resources Canada Baffin Bay geoscience mission had to be cancelled, as no charter was available for the required time frame to conduct the mission.
With regard to part (f), (i) Commissioner Thomas; (ii) September 13, 2016; (iii) Gregory Lick, Director General, Operations; (iv) Memorandum for the Commissioner Vessel Life Extension of CCGS Hudson; (v) The memo seeks effective project approval and spending authority to proceed with the vessel life extension of the CCGS Hudson, at a cost of $26.6 million. The memo also explains that the department will manage project expenditures until the funds become available in fall 2016. (vi) GCCMS: 2016-012-00707; EKME#3656821.
Not all briefing notes are included, pursuant to the government security policy and/or the Access to Information Act.