Mr. Speaker, with regard to costs associated with the Canada Infrastructure Bank, CIB, until March 31, 2018, the total costs of managing the bank are broken out as follows: (i) leases: $ 90,461.35; (ii) salaries of full-time equivalents and corresponding job classifications: $160,170.25, for the job classifications of interim chief investment officer, office manager, and administrative assistant; and (iii) operating expenses: $1,824,457.
With regard to (b) (c) and (d), the CIB continues to engage with stakeholders in the public and private sectors to formulate a pipeline of projects for potential investment. As of March 31, 2018, no project had been approved for investment by the CIB. The CIB’s fiscal year end is March 31 and therefore information for the period of April 1 to April 27, 2018 is not currently available.