Mr. Speaker, with regard to the green and inclusive community buildings program, of the $1.5 billion in funding to be delivered, since the program’s announcement on April 14, 2021, members should please note that Infrastructure Canada provides funding for public infrastructure projects through various programs to provinces, territories, municipalities and other recipients. This response is based on federal funding commitments and does not necessarily reflect when project spending occurred.
Members may refer to the attached annex for information with regard to projects approved to date.
With respect to part (b), all applications are reviewed for eligibility against the following criteria: The applicant must be an eligible applicant type; the applicant must be an eligible applicant type; the building/asset must be an eligible asset type; he building/asset must be a non-commercial community-oriented structure or space that provides open, available and accessible community services to the public; the applicant must have authority over the asset either as the asset owner or by having secured an agreement with the asset owner to carry out the project; the project must be implemented no earlier than April 1, 2021, and no later than March 31, 2026; for retrofits only, the applicant must submit their building’s structural information, energy profile and greenhouse gas, GHG, emissions using the RETScreen Expert software; for retrofits only, the project must not lead to an increase in GHG emissions in the building’s operation; impacts of climate change have been assessed and considered for the project; the applicant must commit to securing the necessary capital to proceed if approved for federal funding; the applicant must provide all necessary data and supporting documents; the applicant must attest to the manner in which the project will meet relevant building and construction laws and regulations, including completion or planned completion of such environmental assessment and consultation as may be required by federal and provincial/territorial governments; and the applicant must attest to the manner in which the project will align to the building standards and codes that apply to the jurisdiction of the existing building, as applicable.
With respect to part (c), these are the criteria used to assess and evaluate applications. For retrofits, the following criteria apply:
Construction start date: Projects that begin sooner will receive a higher score. Located in and demonstrates the ability to serve one or more communities with high needs: Projects that provide greater benefits to high need communities will receive a higher score. Increased accessibility: Where applicable, projects that demonstrate an intention to exceed (rather than meet) the highest standards for accessibility will receive a higher score. GHG reductions: Projects that demonstrate the ability to achieve greater GHG emission reductions relative to the building’s baseline will receive a higher score. Energy savings: Projects that will achieve at least 25% in energy efficiency improvements compared to the building’s baseline energy consumption, as calculated with the RETScreen Expert software, will receive a higher score and are more likely to be selected for funding; in select cases, projects with lower energy efficiency improvements could be considered and selected for funding. Climate resiliency and best practices adoption: Projects that demonstrate strong climate resiliency considerations and measures will receive a higher score; projects that provide reasonable and accurate detail for why climate resiliency is not relevant to their project will not be subject to this criterion and will be assessed relative to other project merits. Confidence in delivery/risk: Projects that demonstrate strong risk assessment and mitigation measures will receive a higher score.
Continuous intake retrofit projects with total eligible project costs between $100,000 and $2,999,999 are evaluated on a continuous basis, with projects needing to meet or exceed a minimum point threshold in order to be granted funding. Retrofit projects with total eligible project costs between $3,000,000 and $25,000,000 are evaluated on a competitive basis, with projects being scored and ranked against one another.
For new builds, the following criteria apply: Construction start date: Projects that begin sooner will receive a higher score. Located in and demonstrates the ability to serve one or more communities with high needs: Projects that provide greater benefits to high needs communities will receive a higher score. Increased accessibility. Projects that demonstrate an intention to exceed (rather than meet) the highest standards for accessibility will receive a higher score. Zero-carbon design standard: Projects that are designed to meet net-zero carbon performance without the need for a transition plan will be scored higher; projects that are exempted from this standard will not be subject to this criterion and will be assessed relative to other project design merits. Climate resiliency and best practices adoption: Projects that demonstrate strong climate resiliency considerations and measures will be scored higher; projects that provide reasonable and accurate detail for why climate resiliency is not relevant to their project will not be subject to this criterion and will be assessed relative to other project merits. Confidence in delivery/risk: Projects that demonstrate a strong risk assessment and mitigation measures will be scored higher.
All new build projects are evaluated on a competitive basis, with projects being scored and ranked against one another.
All of the above information can be found in the green and inclusive community buildings applicant guide at https://www.infrastructure.gc.ca/alt-format/pdf/gicb-bcvi/GICB-Applicant-Guide-BCVI-Guide-du-demandeur-EN.pdf