With regard to the Windsor-Detroit Bridge Authority (WDBA) and the Hydro One Conduit Project: (a) did the WDBA consider Farhad Ganji to be in a conflict of interest by managing the CIMA+ review of the WDBA Hydro One Conduit Project as a WDBA employee and former CIMA+ employee; (b) who made the determination to have Farhad Ganji be a lead in the review; (c) to whom did Farhad Ganji report, and to whom did that person report to at WDBA for the WDBA Hydro One Conduit Project; (d) what is the position of the WDBA regarding the independent engineering findings of Kinectrics, Geotherm and Brierly that the Schedule 40 pipe was the wrong pipe to be specified for this project; (e) if the WDBA disagrees with the findings, what evidence is the disagreement based on; and (f) what differences are there between the original work specifications and the second specifications to address the need to conform to the required specifications of Hydro One?