Natural Resources committee Thank you.
December 13th, 2016Committee meeting
James Gandhi
Natural Resources committee Yes. To some extent, it is quite possible. What we have adopted for the Darlington refurbishment program in partnership with OPG is to create a full-scale reactor mock-up. This decision was made based on the lessons learned from the Bruce refurbishment and the New Brunswick Power
December 13th, 2016Committee meeting
James Gandhi
Natural Resources committee Regarding the nuclear materials for the CANDU industries, we are mostly self-sufficient. We have the materials. We can source this most of the time from Ontario or Canada; however, there are certain types of steel or metal that we have to import from other countries. Nuclear has
December 13th, 2016Committee meeting
James Gandhi
Natural Resources committee The contract for Darlington is a fifty-fifty joint venture between SNC-Lavalin and Aecon. It's a two-phase contract. The first phase of the contract, which is definition, is $600 million. The second phase of the contract, which is execution, is $2.75 billion. Aecon is a 50% partn
December 13th, 2016Committee meeting
James Gandhi
Natural Resources committee For the Darlington project, total refurbishment, it's close to 14,800 jobs, direct and indirect. Aecon is playing a significant...a portion of the significant scope of this Darlington refurbishment contract.... At peak, Aecon is expecting to hire close to 1,800 trades and 400 sta
December 13th, 2016Committee meeting
James Gandhi
Natural Resources committee Good morning, Mr. Chair, committee members, and Mr. Plummer. I thank the committee very much for inviting Aecon to express our views on some very important topics. I feel honoured to present my views today. I'll take this privilege to start with a brief introduction about Aeco
December 13th, 2016Committee meeting
James Gandhi