Oh, that's perfect.
Thank you, Mr. Chair.
We have heard this for a decade, but we also heard during testimony at this committee that one of the biggest frustrations companies face when trying to get major projects built in Canada is that government approval deadlines often don't mean very much. The government is obviously promising to make a decision within one year, should this legislation come to pass, but within it, if federal departments can repeatedly extend deadlines or pause an assessment, that one year can quickly turn into something much longer. Meanwhile, companies are left waiting, investors are wondering when construction will begin, and communities are missing out on jobs and economic opportunities.
What this amendment would do is put some discipline into this process. The federal government would have a maximum of 90 additional days to extend or suspend an assessment, rather than being able to keep adding delays at different stages throughout the process.
Every extension would also have to be made public, including why it was needed, how much time it added and how many days the government has left of its 90-day extension clock. If two federal delays were to happen at the same time, those days would only count once. If the government were to miss a deadline, it would have to publicly acknowledge that failure and provide updates every 30 days thereafter.
Importantly, this amendment would not interfere with indigenous consultation or punish companies that need additional time to complete their own studies. Those delays would not count against the government's 90-day allowance, and they would also not mean automatically approving a project when a deadline is missed.
In my view, this amendment would bring greater accountability, transparency and predictability to a system that desperately needs all three.
I would just like to quickly ask the Impact Assessment Agency whether I am correct in my assessment. Going through the Impact Assessment Act, as amended by Bill C-39, it seems as though there are 10 different provisions that would allow deadlines to be extended or suspended at different stages throughout the projects, including one at the company's request. Is that an accurate reading of the Impact Assessment Act as amended by this legislation?