I'll speak slower. Thank you very much.
We have lots of time, so I will take the time to read my explanation, but I won't start from the beginning to save a bit of your dignity.
I was talking about the list of federal authorizations required. The organization has to provide a list of the federal authorizations and requirements that materially affect the project's timelines. For example, it has to list the environmental authorizations, permits and other federal requirements that could delay or stop construction.
The document also has to contain recommendations for improving timeliness. The organization can recommend ways to reduce administrative timelines, improve coordination between departments, consolidate processes, and recommend authorizations or exemptions that may be granted under the act.
In addition, the document must contain completed assessments and consultations, further to point (c). The organization can attach completed assessments, results of consultations and other information available in relation to the project, and the reasons for its decision.
Consider a scenario where the responsible organization sends a complete request regarding Alto on March 1. The minister would have to make a decision within 45 days of receiving it, so by mid-April, taking into account the statutory calculation and the timelines, among other things. The minister couldn't just let the request sit for months.
Proposed subsection 5.2(2) adds another obligation. If the minister feels that the information required under subsection 5.1(3) hasn't been provided, the minister must promptly notify the organization and indicate what information is missing. It's important to clarify that it's not explicitly stated that the 45‑day time limit is suspended when information is missing.
Here's what the amendment doesn't do, because it's important not to ascribe a broader scope than it has.
Here's what the amendment does. It provides for a request for national interest recognition, which doesn't automatically guarantee that recognition; a process based on reasonable grounds to believe that the project is necessarily in the public interest; recommendations to speed up authorizations; automatic exemptions from existing legislation; a decision by the minister within 45 days; the fact that the Governor in Council will necessarily make a favourable decision; the sharing of assessments and consultations; and the completion of all project studies.
I'm almost at the end of my document.
What is the political significance of CPC‑14? The amendment upholds four important principles.
The first is accountability. The government must be able to explain why a project warrants national interest recognition. That's important.
The second is transparency, which we've talked about but haven't really been able to achieve. The request will have to include relevant findings that emerged from the review and consultation process.
The third is predictability. A request can't go unanswered. The minister will have to make a decision.
The fourth is administrative efficiency. It is possible to accelerate project timelines by improving conditions without undermining statutory protections.
I will leave it there, fellow members. I am sure members will have comments, which I can address afterwards.
Thank you.