Yes. These are transition provisions to figure out what happens to a project once the act receives royal assent and comes into force, meaning which projects transition to what I'll call the new act and which projects stay under the old act. That's determined by where a project is in the impact assessment process.
The clause was designed to make reference to a specific phase under the IAA. The problem with this is that certain projects are still in the system because they were under the predecessor to the IAA. By being overly specific here and referring to a clause in the IAA as it currently exists, we've orphaned projects that predate the Impact Assessment Act.