I would like to clarify what schedule 5 in the Impact Assessment Act does. I'm afraid that maybe there's a misunderstanding about what schedule 5 is in impact assessment.
Under Bill C-39, one of the core initiatives that is being put forward is that impact assessment and permitting could happen at the same time, rather than one after the other, but not all permits could benefit. The proponent can't do that for any and all permits. It's only for permits in schedule 5. That's all that schedule 5 is about. It's confirming which permits could be processed at the same time as the Impact Assessment Act.
There is no circumventing of any regulations or permitting requirements. All permitting requirements must still be met. The only thing the Impact Assessment Act is proposing here in Bill C-39 in schedule 5 is listing which permits could be processed concurrently to the impact assessment process. That's it.