Under the Building Canada Act, if a designated project under that act is also a designated project under the Impact Assessment Act—which will not necessarily be the case—an impact assessment will be required of that project.
I think there was mention of five projects that were announced. First of all, those projects were referred to the major projects office. They haven't yet gone through the process to be formally listed or scheduled under the Building Canada Act. Three of those projects have already completed assessments, so they won't require any further assessment by us, because those have already completed assessments, and the other two projects are not subject to the Impact Assessment Act, so we won't interact with them under the new act.