Well, frankly, it's not great. I don't know whether to sugar-coat it or not.
The Pathways project is a leading CCUS project that's well supported by the current government. The project economics, to be frank, are very challenging. Even, as I said, if you had an ITC that covered 100% of the capital, you still have expensive projects to operate and a carbon market that's been, to date, fickle.
Now, having said that, the Prime Minister has been very clear that, as part of this MOU, the carbon price will rise. I think it was $130 or $140 per tonne by 2040, with an interim step in 2030, but I may have those numbers wrong. That will help.
It's also worth noting that the companies themselves won't do this for free. With any carbon capture project, companies need to have some return on the capital they employ. You have to make sure that the scenarios you're running don't assume a 0% return on invested capital for the companies, because—