First of all, I was not expressing frustration. What I was expressing is that the way our regulatory processes work in Canada is that they're all done sequentially. You go through an environmental assessment. Then you go through various departments to get permits.
For example, one of our projects, Roberts Bank, has been in permitting in Canada for 10 years. I happen to be in Vancouver. We happen to be working on that project. In fact, I'll talk a bit about Pacific link: It was different.
Ten years of consultation still have not permitted that project, and we do not have the ability to build the piece of land in the port. That was where the frustration was coming from, for me personally.