Thank you, Mr. Chair.
Good morning, gentlemen.
In September 2007, one week before the end of the qualification process—that was when Michael Fortier was Minister of Public Works, as we know—the procurement documents for the rehabilitation of the North Towers on the West Block were apparently changed.
A number of firms involved in the process state that, without that change, LM Sauvé would never have won the contract and would never have qualified.
Is it true that, without that change, LM Sauvé would never have won the contract?