Thank you for the question.
Mr. Chairman, there were two amendments that were made just about eight days prior to the closing of the contract. I'll refer to them as they are posted on MERX, as amendments 3(a) and 3(b). Amendment 3(a) was at the request of LM Sauvé, and the request specifically was that a general contractor—keep in mind there was a general contractor and six subtrades—supply the names of two subcontractors in each subtrade. The question from LM Sauvé was, as a masonry company and as a general contractor, would they have to submit the name of a second subcontractor--in fact what would have been a competitor--on their bid in order to pre-qualify.
The second amendment was based on a request from a masonry design centre to reduce the level of experience on previous masonry contracts. The experience that you had to submit...[Technical Difficulty--Editor]