I don't think so. It was more a lack of knowledge of where we sat in the process, as the process was taking place. We would get one level of approval and wonder if that was the final approval. And then we'd get to another stage and wonder if that was actually the final approval. I remember when we did get the final go-ahead to ship the equipment, I wasn't even clear if that's what we were able to do at that point. So I had to send back a clarification e-mail asking if that meant we could send the equipment and send an invoice.
On November 1st, 2011. See this statement in context.