For the West Block program, the projects approved are in the order of $1.171 billion. Those are approved projects. For the Wellington Building rehabilitation, the $425 million is in the overall rehabilitation budget. Once again, that includes contingencies, consultants' fees and the like. My budget for the West Block, the project that Mr. Doucet was talking about, is $863 million. The Sir John A. Macdonald Building rehabilitation comes to $99 million.
Those three amounts are final and approved, for all the renovations to be completed.