There was a very short contingency plan for the transfer of the data. Immediately after wave one, if there had been problems in the data transfer, then they could have stopped. There were no problems with the data transfer. That's how the project was planned. There was no fatal issue with the data transfer.
I'm thinking of the employees who are listening. That has nothing to do with their pay because it's actually the ongoing pay that we're doing.
The problems started when all of the change requests, the actions, the overtime, and all of those things that we had to do either manually or there was more that we had to do. The capacity was not there to be able—