As the first step, once we have awarded the contract with the ship designer, we will obviously plan the next few years of work of design. Once we have these first engagements, with the actual contract awarded, we will be able to refine the schedule.
We're expecting two to three years of design work before we can actually cut steel. Let's say early 2019 to 2022, then cut steel, with a delivery in the 2025 time frame.
Again, at this stage we have identified a preferred bidder, but we have not sat down and awarded the contract.