It would have a schedule and cost impact. There's no question about that.
For all of these precursor projects—the archeological work, the removal of underground services and the construction road—the devil would be in the details of how much we'd be able to do given that type of motion. That work was planned to essentially start now, so you would have essentially, I guess, a three-month impact with the escalation costs associated with that, which are significant.