I'd really appreciate it if you could.
Thank you for the very helpful Gantt chart. I look down it and see that you divided things up timewise. The first one is April to September—we're in that period now—when certain things commence.
The one thing that ends in September 2019 is the Centre Block decommissioning. That is done sometime in September. A number of things start in the period we're in now, and continue on post-September. The one that strikes me most significantly is the schematic design issue. It seems to me that starting that process before the next election is highly problematic in terms of getting input from the House of Commons and us.
Additionally, I should note that construction management—the tendering—starts in September, so there may actually be tenders that are put up before Parliament or the House of Commons has a chance to do any oversight. We are going to be in the middle of an election; no one will be in a position to do oversight. I think that is problematic.
In the interest of the House of Commons—which, after all, is the body that oversees expenditures—having its appropriate share of control over this, both on the costs side and what the costs are being incurred for, I encourage you to put that off until the post-election period. I recognize that this would not speed up the project, but this is one of those times when I think it might be appropriate. My colleagues may contradict me on this point, but that's my initial observation. That is a problematic timeline. I just throw that thought out for your consideration.
Mr. Malcic, thank you for being here. I found your comments with regard to the architectural issues very informative. I did have an administrative question for you. From whom do you formally take your marching orders or instructions? Or, if you wish, who are you contracting with?