Since the long-term vision and plan was recalibrated in 2006-07, there's been quite a strong track record of delivering projects on schedule and on budget. Consecutively, 24 major projects were delivered on time and on budget. I can walk through a couple of those, if that would be helpful.
Phase one of the visitor welcome centre, for example, was $129 million. That was a 5,000 square metre facility, which gives you some benchmarking for some cost comparisons. Approximately 5,000 square metres and $129 million were delivered on schedule in 2018. This building was delivered for $863 million on budget in 2018.
The Senate of Canada Building, which also included other space for senators, was delivered in 2018 for $269 million, again, on budget.
The Wellington Building was delivered in 2016, at a value of $425 million.
The old Bank of Montreal, now the Sir John A. Macdonald conference facility, was delivered in 2015 for a cost of $99.5 million, again, on budget and on schedule.
Those are some examples. We can go through some more, if you'd like.