Sure.
On the consultation part, just based on the conversation we've had today, it's going to take more than nine months. You're going to need provincial and federal co-operation. That's why we're recommending that the consultation not have a prescribed time limit on it.
In terms of a labour supply coordinating committee, I can tell you how our unionized industry works. Our IVP, our international vice-president for the electrical workers, could send out a note to all the locals across Canada and would know within a day how many workers are available, how many workers are out of work and how many workers are working. We could do that for all of our 14 different unions. We'd be able to feed that into a secretariat that could help match that up with the Major Projects Office.
For example, LNG phase two has workers on site right now. It's probably going to start peaking in Q2 next year. How many tradespeople do you need? What are the tradespeople you need at the beginning of the job? Where are you going to get them? We're going to get them mostly from British Columbia. Do we have enough supply in British Columbia? You're going to need carpenters, form workers, labourers and operating engineers for the first phase of that job. What's the labour availability in British Columbia right now for that major job, and similarly for the pipeline?
Feed that into this secretariat. Have government involvement as well, with Statistics Canada and labour market people from ESDC, so that we can have a real-time labour analysis of what workers are available through our union halls. That's going to help successfully complete these projects on time and on budget, but it doesn't happen.