Thank you, Rita.
Niik Steel is one of the largest structural steel fabricators in the Vancouver area, employing more than 100 people. We fabricate the steel that holds buildings up: columns, beams, brace frames, stairs and platforms. The steel goes into commercial and residential towers, hospitals, schools, community facilities, affordable housing and industrial projects. It's mostly in British Columbia, with some work in Washington and Alaska.
I would like to show you what the issues Rita described look like on our shop floor.
The products that we struggle most to get are steel plate and coil. Plate goes into almost everything we build. A column cannot leave our shop without its base plate. When plate is late, the whole job waits.
For a fabricator in British Columbia, the problem is sharper. Canada's domestic mills are thousands of kilometres away, so every tonne carries weeks of transit time and real freight costs. Western fabricators have always filled that gap with imported steel. Today, the import quotas are often used up within hours of opening, usually by the biggest buyers and traders, which can commit to huge volumes on one day. Fabricators like us cannot win that race, so either we pay the higher tariff or we wait. Neither option works when we have signed a fixed price, a fixed schedule and a liquidated damage class.
Let me give you a real example to illustrate the challenge. There is a municipal project involving three towers and a community centre. When we signed the contract last December, steel was about 60¢ a pound. Within a year, with tariffs and TRQs, the same material reached $1.32, which is more than double. As a result, one of those three towers is now on hold. The demand for that building is still there. It has stopped because of what the steel now costs.
Fabricators work on fixed-price contracts, usually with no escalation or tariff clause to protect us. The mills sell at market price, so cost increases pass straight through to us. We are the ones absorbing them. At the same time, we are facing a real shortage of plate and coil. Every delay turns into commercial and legal risk for our companies. Over time, that weakens our ability to compete, and it's already shrinking our industry.
That brings me to my biggest concern. When owners face such risk and this kind of uncertainty, they don't wait. They redesign with other materials. Once a project switches away from steel, that work doesn't come back. It is lost to Canadian fabricators, lost to Canadian mills and lost to every worker these measures are meant to protect.
Thank you. I'll turn it back to Rita.