To ensure the safety of our personnel, as the minister is saying, the supplementary estimates (C) include $5.8 million in capital funding for projects to upgrade security at our bases. The funding is being carried forward from fiscal year 2016-17 to 2017-18 due to some delays in the project approval.
We have four projects we are funding from this for physical security upgrades in these estimates: work at the Defence Research and Development Canada facility in Halifax, upgrades to physical security in Dundurn, updates to the security barrier on the South Perimeter Road in Trenton, and the configuring of Alert Boulevard in Trenton.
As well, in addition to those four projects we have these two projects in progress: entry control facilities at Borden and perimeter fencing for facilities at Shilo.