At the end of March 2007, there was an investment of approximately $300 million for developing the ACR. I want to ask you questions about the risk this has introduced into the marketing plans of AECL for the ACR reactor and about, basically, the comment with respect to pre-licensing being a major constraint for AECL in developing this in the future. The costs necessary to develop the facility by 2016 were estimated at $400 million, yet CNSC found it necessary to withdraw its service of pre-licensing, citing resource constraints.
I recall, when looking at the department's estimates, that there was an allocation of around $3 million for these pre-licensing activities when that whistle was blown. Yet I believe those dollars were never spent. Was there any insight you gained in the audit as to why CNSC made the abrupt change in pre-licensing when it looked like there was funding provided for that task?