Noront's plan is to be in commercial production by 2016. We have filed our project description with CEAA, and it's already gone out for the first round of public comment. Reasonably speaking, we'd expect that process to last another nine to 12 months before the CEAA process is through.
The final permits for the mine development would be sometime in mid-2013 to the third quarter of 2013. That's the timetable we're working towards.