Mr. Chair, as I said in my opening remarks, the National Energy Board will issue the certificate in the next couple of days. I was in Edmonton and had a chance to meet with workers and some of the contractors. They're ready to get down to work and they're preparing some of the work that does not require regulatory approval. The company can start mobilizing the contractors and subcontractors. They can start mobilizing their workers. They can start bidding for reconstruction work that is necessary and they can start applying for permits.
As we heard from the Trans Mountain Corporation, they're planning to put shovels in the ground by September. The goal is to complete the construction by mid-2022 so that we can start flowing the oil to markets beyond the United States.
It is very important, Mr. Chair, to understand that 99% of the oil we sell to the outside world goes to one customer, which is the United States. It is a very important customer for us. We need to expand our market with them, but we need to have more customers than one, because we are selling our oil at a discount and losing a lot of money. Over the last number of decades, the situation has remained the same. We want to make sure that this situation changes. That is why getting this project moving forward in the right way and starting construction is very important, not only to Alberta workers but also to all Canadians.