The energy requirements for the province are managed by the IESO. We're a generator, so we provide energy to the province.
The refurbishment of Darlington will take 10 years. That's the time span. We're seeking to operate Pickering right through that period. The completion of the refurbishment coincides pretty much with when Pickering will cease commercial operations. The real question will be how the energy that Pickering currently produces is going to be provided to the province. The IESO will look at the existing capacity, first and foremost, within the province, and that will likely come from the existing gas generation within the province, as well as some renewable projects and existing renewable energy. That's the current plan.