In terms of the refurbishment cost, the overruns were $1.4 billion. The energy replacement cost was $1 billion. Those costs are incorporated into the price of Point Lepreau over the life of the plant. The cost of the life of the plant is still 8.3ยข per kilowatt, which is extremely competitive.
In terms of discussion beyond that, this is still a court case, and I'm not allowed to discuss it in any more detail as far as the pending lawsuit is concerned and how that's going to be resolved.