Remember, not only do these transmission lines allow us to export; they also allow us to import. The main value for this line is our ability to import and defer the need to build new generation resources some time in the future. We felt there was value in the line even if Manitoba Hydro had to bear the whole cost in both Canada and the United States. Through our power purchase agreement with Minnesota Power, their ratepayers were able to pay for 25% of the cost of the line, so it became a value proposition to have them as a partner.
We're much better off having them contribute to a line. All the electricity that will flow on that line is Manitoba Hydro electricity. Whether it's purchased power or electricity that we're exporting, the value is almost all to us. What we have with a partner in the United States is someone who's willing to fund a portion of a line that we would otherwise have to pay the full cost of.