I can't say with definiteness, because I'm not a developer. However, I can say that currently one of the biggest impediments to natural gas power investment is equipment lead times. Right now, you can't buy a turbine for delivery before about 2032. We're at a point at which the supply chain is almost more of a limiter than any permitting process.