Building a project in the Arctic definitely has some special considerations that would extend any permitting process. Obviously, we had to consider Inuvialuit rights in the sensitive environment of the Arctic, but I would say that a typical project of this scale is usually done within a province or territory—even in the States it would be within a state—and it should be a six- to nine-month process, or maybe a 12-month process. Taking into consideration the Arctic, there would be a bit more time, but four years did seem like a long time.