Thank you.
Mr. Chair and honourable members of the committee, thank you for inviting me today.
My name is Dr. Thomas Walker. I'm a professor of finance and director of the L. Jacques Ménard BMO centre for capital markets at Concordia University. I also serve on the scientific committee and as co-lead of the Volt-Age sustainable electrification program. Additionally, I serve as director at the institute for sustainable finance at Queen's University.
Earlier in this study, witnesses told this committee that doubling Canada's electricity grid by 2050 will cost between $1 trillion and $2 trillion. Governments and taxpayers cannot pay for this alone. The vast majority must come from private institutional investors, such as pension funds, insurers and banks. My written brief outlines four financial pillars to mobilize that private capital, which I will summarize today.
Pillar one focuses on the de-risking of private capital through blended finance, public-private partnerships and indigenous equity. Blended finance means using targeted public money to absorb early project risks so that pension funds can meet their fiduciary duties and invest at scale.
In March 2026, Parliament expanded the Canada Infrastructure Bank's capital envelope to $45 billion. Deploying that balance sheet for first-loss loan guarantees, revenue insurance and public-private partnerships lowers the risk for private lenders. Lower risk means lower interest rates and lower electricity bills for Canadian families.
A prime example of de-risking is indigenous equity financing. As the first—