I'll give an example of that. The Dow and X-energy project in Texas submitted its construction permit application in March 2025, and the U.S. regulator established an 18-month review schedule.
In Canada, Ontario Power Generation applied for its Darlington reactor in October 2022 and received its approval approximately 29 months later.
Based on your experience, what does the difference in timelines mean for project costs as well as construction schedules?