The final design was never approved. That's why we're continuing to have discussions and why I continued to meet with the board over that period of time.
In the first year we put aside $8 million. In the beginning, it's planning phase: looking at finding facilities, doing research, looking at what the demands would be, starting to negotiate the lease cost to find a facility. For that planning activity, $8 million was allocated for this year. Only $2 million was expended, partly due to circumstances. We had an election in there, and we had to get final approvals after we saw what the fiscal situation was, after two independent reviews.