Thank you.
I'm looking at your chart. Exhibit 2.5 speaks to “Identification Phase”, “Options Analysis Phase”, and “Definition Phase”. I have a specific question. This project initiation started in January 2010, and I'm just trying to understand this life cycle costing, because this chart indicates that the total project life cycle costs are estimated during the options analysis phase. Then, during the definition phase, total project cost estimates are revised. So this whole process is one of a moving target and always a revision of costs.
Obviously, as you move further forward in a project, you become more knowledgeable, so I'm trying to understand the fact that life cycle costing, you indicate, wasn't provided in full by the department. But this chart suggests that it would have been premature to have those costs in full, considering where we actually are in the project management cycle. Can you comment on that?