Well, certainly the department did agree with our recommendation.
I think it is important to recognize that we started auditing this process very early, perhaps earlier than we would normally audit a process. There was, though, something for us to audit, which was the selection of the yard, so we were able to do that. Again, that's why we haven't audited some of the cost numbers. We recognized that it's still too early to treat those as real estimates as to what it's going to cost to build the ships.
We thought it was important that parliamentarians understand that there are budget caps and those budget caps seem to be a budget tool to maybe put some discipline into the system, but people need to be aware that choices are likely going to have to be made. We just want to make sure departments keep the Treasury Board ministers up to date whenever they are faced with having to consider those types of choices.