We need to get the dates straight here, and whether you're talking about my transition binder or the minister's transition binder. I came in April.
The Gartner report was requested by the Treasury Board. PSPC did their own report through the gating processes, and that's the S.i. report you heard about. That report said that considering everything, it was ready to go.
Treasury Board decided to order a specific report, the Gartner report. I'm not sure what the genesis of this was, but there was probably some reason to do it. It was delivered to Treasury Board. It was shared with PSPC, if I remember correctly, in January. I'd have to go back to that date.... I'm told it was January 29. It was also communicated by the comptroller general to the associate deputy at PSPC.