First, I would say that we accept all of these findings and the implications of the findings. As I said, we found them ourselves in our own internal audit.
Second, we make use of the resources that we have available to us at any given time, and we have to allocate those resources on the basis of current need. In some cases, the more urgent security needs would account for the delay in identified projects or the pacing of projects.
Third, as I indicated, and as the Auditor General's office indicated, the documentation of projects both for tracking needs and for tracking implementation was, as is so often the case, not there. We have now put those tracking systems in place.
These cases that are described are accurate, and we have put in place, as I indicated in my comments, the measures to know exactly where we are in our projects and to make decisions on the basis of risks as they emerge over time.