During our audit period, we saw that the department was taking steps to improve the way they monitor the successes of their projects. In exhibit 4.7, there is a list of the core project-level performance indicators that they need to put in place. As we just said, these new indicators were applied to nine projects so far, but of the 116 that are currently under way, another 107 need to be adjusted to take into account these performance indicators.
Really, the consequence of this so far is that by not applying the proper project-level indicators, the department has been unable to demonstrate, basically, the outcomes of the program overall because they don't have the information they need to show results for the whole program.