I apologize. Let me repeat that.
I would say that, going back to 2010, when the previous OAG report came out, we made some significant efforts, working with our partners in the parliamentary precinct, to streamline a decision-making process and better support it.
We have monthly meetings at senior levels, if not more frequently. We have touchpoints built into the process. Most recently, based on the recommendations of the Auditor General in this report, we added a semi-annual report, which the Minister of Public Works has tabled with the Speaker of the House of Commons, as well as the Speaker of the Senate. It outlines our progress to date on Centre Block and also puts en vitrine outstanding decisions that need to be made in the upcoming time. Some are joint decisions between both houses, some are broader across the parliamentary partners and some are unique, but at least we have a way to identify those that are there and the timelines required.