There are a couple of items that maybe I'll just put in there.
As reported in the Auditor General's report, the cost was $32 million. The final cost was actually $33 million—just for reference and for a bit more background. The initial engagement with McKinsey was estimated at about $18 million for a six-month contract. Then, because of the success and the value created in the project, it was decided to extend that contract, which ended up with the ultimate cost of around $32 million. It was extended to about 12 months, as opposed to the six months originally contemplated.
I apologize, but was the remaining part of the question the justification?