Page 13 of your report, paragraph 31, states the following:
These detailed cost estimates have to be finalized and delivered to the Treasury Board of Canada Secretariat by December 2026 if additional funding beyond the originally approved $565.9 million is to be allocated to the project.
In June, the projected costs were $350.6 million, according to Minister Lightbound. In December, the project was budgeted at an additional $200 million. You're now already estimating that this amount will be exceeded and that additional amounts will be needed for what has already been spent.