I’m going to ask my question again.
What we’re talking about here is a proposal I made in which I used the terms “cost overruns” and “new funds”. We’re changing the words to convey a different meaning. I’m perfectly fine with that.
I’m just wondering if, by using those words, it includes every stage where we requested a cost increase and a justification explaining why those amounts weren’t high enough. We went from about $1.7 billion to nearly $2.5 billion, then to $3.3 billion or $3.5 billion, then to $4.4 billion, and finally to $6.6 billion.
When requesting the estimates and costs, do we also have what was planned for those stages? We have that information for the stage where we reached $6.6 billion. Was the information collected at each stage?
That was the point of my question, and it is asked in good faith. You may repeat more or less the same thing to me each time, but I hope we will reach a consensus.