Certainly. This is the first time Canada has developed infrastructure for a fifth-generation capability. It's highly complex for some of the reasons that we've already covered. We've learned a heck of a lot, actually, as part of this design process. We've been working very closely with EllisDon, the contractor. Through the design predecision, we learned a lot of lessons that we applied in the design post decision, as we made the adjustments to the new requirements.
We are in kind of a constant learning mode on this. We will be applying those lessons very much in the context of future acquisitions, for sure.