I think there are two parts to the SMR technology. I'd call one a grid scale, which is what we are setting out to build at our Darlington site. They're about 300 megawatts in size, which, roughly speaking, would electrify 300,000 houses, give or take a few. We will ultimately put four of them at our Darlington nuclear site. The community is very used to nuclear in Clarington-Durham.
The second application, which was referenced a little earlier, was really the microreactors, and these are the smaller ones that you might put at a mine site or in a remote community, places where you need less load—they might be five or 10 megawatts relative to 300—and go from there.
The two different applications will move into two different spots.