I can indeed confirm that there are no missing projects, and we have provided the PBO with a full accounting of the projects. At the time, there were 52,000. Now there are 67,000, because every day there are new projects that are approved. We worked with the 21 departments to provide the information to the Parliamentary Budget Officer.
I can go further and say that we have a funding table on our website with all of the programs for the $188 billion. In the Auditor General's paragraph 9.40, she says that the project list in the funding table does provide a full accounting for the plan, so there is no question that we have been able to report on the full plan and provide the information to the Parliamentary Budget Officer and the Auditor General.
That said, there are different levels of information that are available, such as for the gas tax. We don't get the same level of detail as we do for other programs that apply directly to us or other federal departments.